Case Studies

Harley Haddow

Our Mission

The project involved the stripping out and installation of new services to suit the new office fit out arrangements. JGM undertook the principal contractor role, as well as the installation of all services. The design intent was an open office environment with all services being exposed. This required a significant degree of design and careful planning of the works. A stylish, neat and coordinated services installation was fitted, against the new office, furniture and operational layouts.

Client Harley Haddow Consulting Engineers Principal Contractor JGM
Duration 2
Months
Value £196
Thousand

Electrical

  • Installation and upgrade of main and sub main power.
  • Installation of new containment for electrical and data services.
  • Installation of new lighting, power and control arrangements.
  • Modified fire alarm and specialist services.
  • Data network installation.
  • New security, access control and IT arrangements.

Mechanical

  • Installation of new heating, cooling systems and controls.
  • Modifications to the core ventilation primary and secondary networks.
  • Alterations to existing heating and public health arrangements.

The results

The new services installations were presented in a neat and coordinated manner, allowing for their exposed installation.
Core services were also amended to take account of the fit out requirements. The new services networks offer a pleasant working environment for the staff in moving their business forward.