Heriot-Watt University: Language Labs

Our Mission

The project brief was to transform two large classroom arrangements into a fully fitted out language lab teaching environment. Both existing areas were isolated for the duration of the works. However, it was required that noise be kept to a minimum, as the existing building was still being used as a teaching environment. JGM was responsible for the standard services works, as well as the servicing and control of the master stations and the field language lab cubicles.

Client Heriot-Watt University Principal Contractor SJS
Duration 3
Months
Value £217
Thousand

Electrical

  • Coordinate installation drawing exercises.
  • Installation and upgrade of main and sub main power.
  • Installation of surface and recessed containment for electrical and data services.
  • Installation of new lighting, power and control arrangements.
  • Installation of new fire alarm networks, interfaces and specialist services.
  • Installation of IT and specialist lab wiring networks.
  • Testing, commissioning and demonstrations to the HWU protocols.

Mechanical

  • Coordinate installation drawing exercises.
  • Installation of new heating, cooling systems and controls.
  • Installation of ventilation primary and secondary networks.
  • BMS and specialist control networks.
  • Testing, commissioning and demonstrations to the HWU protocols.

The results

A heavily coordinated project. Tested, commissioned and handed over on programme and to budget.

  • Excellent client liaison due to the complexity of working within a live university building environment.
  • Handover of the new services arrangements, including the commissioning and demonstration of the working installations, completed to the Heriot-Watt protocols.