Case Studies

Doune Health Centre

Our Mission

JGM were appointed by Hadden Construction to carry out the full Mechanical, Electrical and Plumbing installation, as well as part of the contractor design package for the new build Doune Health Centre. Crucially, JGM delivered this project both on time and within the budget.

JGM worked on the installation of new Electrical, Mechanical and Plumbing solutions at Doune, as well as designing part of the design package. 

Client NHS Forth Valley Principal Contractor Hadden Construction
Duration 5
Months
Value £350
Thousand

Electrical

Electrically we carried out the installation of a new LV switchboard, as well as LV distribution and small power cabling solutions. For lighting we installed both emergency lighting systems, and general smart lighting solutions for the use in the day-to-day operations at Doune Health Centre. JGM also installed data networking solutions for the centre, including Cat6 structured cabling, this tied in with the majority of security systems including access control, intruder alarms and networked CCTV systems. JGM managed the installation of fire detection and alarm systems, along with disabled refuge systems and ‘panic’ button alarm systems for staff in the centre. For the outdoors areas of the centre JGM installed outdoor lighting solutions to illuminate the surrounding area of the building perimeter. Finally, JGM installed a solar PV system with an uninterrupted power supply (UPS) backup for the critical systems in the health centre.

Mechanical

Mechanically JGM were responsible for the installation of above ground drainage, as well as rainwater goods install. We also installed the external water main and all water services pipework throughout the centre. Air-Conditioning and ventilation systems were also installed, along with sanitaryware. Low temperature hot water (LTHW) heating was installed with a gas boiler solution. Finally, JGM were responsible for the plantroom install and implementation of the building management system.

The results

We encountered a few challenges in this project including delays from the client with the main power, water and gas supplies. Due to the site services coming in much later than originally planned for JGM had to squeeze the full M&E commissioning works into a three-week period with no additional delays to the original client handover date. We worked in conjunction with the main contractor and our own in-house operatives and specialist sub-contractors to ensure that the commissioning was successful, and the handover would be granted as required.

JGM held weekly progress meetings with the delivery and design teams, carrying out risk assessment and issuing method statements for review and approval prior to the works taking place. All working practices were continually updated and managed effectively throughout to ensure the project ran smoothly, due to the delays from the client side JGM adapted working practices to ensure the project was brought back on track as a matter of urgency. Our project managers held daily briefings and toolbox talks as required with the operatives and sub-contractors to ensure that all information was communicated to the individuals undertaking the specific tasks. Additional protection measures were implemented ensuring site safety, including the use of signage to alert our own operatives as well as all contractors and site visitors to the dangers of our works.

JGM managed to ensure the project was completed on time, on budget and to a standard exceeding our client’s own expectations. JGM have worked with Hadden Construction on numerous projects and have built a well-respected and long-standing relationship with the construction firm. We look forward to working with Hadden again in the future to delivery more excellent projects similar to that of Doune Health Centre.

More case studies

Key sectors

Connecting with our clients for success.
Contact Us

Our Accreditations