The fit out project involved the upgrading of the core building services, an increase in the specification of the MEP materials, and the replacement of the existing services within each of the hotel floors, function suites and back of house areas. The installation of the new services required to comply with the latest legislation and regulations for the hotel operator.

The fit out and installation works were undertaken when the hotel was occupied, and functional. Whilst the works were being undertaken, it was critical that the hotel functionality remained fully operational, with no downtime permitted. Careful and detailed planning was required for the heavily serviced core and floor installation works. Noise was to be kept to a minimum also.

Client The Radisson Blu Hotel Principal Contractor Sharkey
Duration 12
Months
Value £2.5
Million

Electrical

  • Co-ordinated installation drawing exercises.
  • Phased work planning exercises – design and installation.
  • Installation and upgrade of main and sub main power, electrical services and hotel suite/room distribution.
  • Installation of surface and recessed containment for electrical and data services.
  • Installation of upgraded specification of internal and external lighting, power and control arrangements.
  • Installation of fire alarm network interfaces and specialist services.
  • New key and guest room control systems.
  • Upgraded front of house and back of house electrical and specialist services.
  • Phased completion and the handover of the building services elements.

Mechanical

  • Co-ordinated installation drawing exercises.
  • Phased work planning exercises – design and installation.
  • Installation of new upgraded specification for the air conditioning, heating, cooling systems and controls.
  • Installation and upgraded ventilation primary and secondary networks.
  • Upgraded mechanical specification and the installation of the BMS and specialist control networks.
  • Upgraded front of house and back of house mechanical and specialist services.
  • Phased completion and the handover of the building services elements.

The results

A heavily co-ordinated project, tested, commissioned and handed over, on programme and to budget.

Excellent client liaison due to the complexity of working within a live hotel and building environment.
Handover of the new services arrangements, including the commissioning and demonstration of the working installations, completed in a phased manner, allowing the hotel to operate.